FOCUS ON ENERGY
Crude Ambitions:
The Lamu Refinery and
What It Means for
Business in East Africa
Seven weeks after the groundbreaking at Mokowe, Dangote’s 700,000-barrel-a-day refinery has machinery on site and tax incentives announced, but no published licence, ownership agreement, or contracted crude. What the courts and the region’s precedents tell business, and what to do now.

On September 30, 2026, President William Ruto and Aliko Dangote broke ground at Mokowe, Lamu County, on the Dangote East Africa Petroleum Refinery, a 700,000-barrel-a-day project at a stated cost of about USD 16,000,000,000.00 (KES 2,079,360,000,000.00). Seven weeks on, machinery is on site, and tax incentives have been announced, but there is no published environmental licence, construction permit, shareholders' agreement, or contracted crude, and the Kenyan project company has not been identified.
The refinery is already in the courts. Chandavai residents have a land petition before the Environment and Land Court at Malindi, which returns on November 24, 2026; a petition for disclosure of the State's commitments is before the High Court; and the PPP Petition Committee dismissed a third challenge on October 30, 2026, for want of jurisdiction. Lamu's earlier judgments are instructive. In Baadi, the port went ahead, but its proponent was ordered to compensate more than 4,700 fishermen; in Save Lamu, the coal plant's licence was set aside for want of effective public participation, and the plant has not been built.
The region's precedents point the same way. Kenya's Mombasa refinery, shut in 2013, shows that a refinery that cannot compete with imports will be idled; Lekki shows that Dangote can build at scale; Uganda's Kabaale refinery still awaits a final investment decision; and EACOP shows lenders adhering to international standards. With Turkana supplying at most one barrel in fourteen, Lamu is likely to depend on seaborne crude and compete on margin with imported products.
The advice is to verify before committing. Contractors should review the licence, permit, and proof of lawful possession before mobilising; suppliers should secure payment from the entity that holds the assets; lenders should make funding conditional on the licence, the resettlement plan, and the Malindi outcome; and businesses at risk should diarise the sixty-day appeal period.